Appolonia Data Center Newsletter – October 2020

Tremendous progress is being made on the construction of the MainOne Data Center project in Appolonia City, Accra, Ghana in advance of Commissioning planned for Q1 2021.

Sequel to the completion of the main building foundation and modular unit platforms; manufacturing of the Data Center prefabricated module; and super structure works of main building ongoing and deck in September as reported in our Appolonia Data Center September newsletter, the following milestones below have been achieved in the month of October:

  • Factory Acceptance Test completed.
  • Main Building superstructure ongoing at roof beam level.
  • Prefabricated modules to be packed and shipped for delivery onsite in November.

The Factory Acceptance Test (FAT) for the modular unit has been successfully completed as all pre-fabricated and pre-integrated components comply with specification and successfully tested to operate as specified. We are preparing to ship these modular units to Ghana by November for installation and final integration.

Click here to read a full progress report on our Appolonia Data Center in our October newsletter.